Todayan hour ago
Project update
CleanSpark posts $987M fiscal 2026 loss as bitcoin output falls 8%

CleanSpark posts $987M fiscal 2026 loss as bitcoin output falls 8%

The miner, which now brands itself a data center developer, reported results for the fiscal year ended September 30, with revenue down 25% year over year to $576.5M.


The fourth quarter alone was profitable at $9.8M of net income, but the full year closed with a net loss of $987.1M ($3.74 per share) and an adjusted EBITDA loss of $304.2M. CleanSpark mined 7,253 BTC, 8% fewer than a year earlier, as average hashrate dropped 21% to 36.0 EH/s.



CleanSpark ended the year holding 13,530 BTC including collateral, worth about $1.1B as of September 30.


The company is shifting capacity toward AI and HPC: it signed a 20-year, $6.6B lease at its Sandersville, Georgia site, funded by $2.276B of 7.875% senior secured notes due 2031, with the first data hall planned for November 2027.